Hysbysiad dyfarnu consesiwn
Cyfiawnhau'r weithdrefn ddyfarnu a ddewiswyd
Adran I:
Awdurdod/Endid
contractio
I.1) Enw a chyfeiriad
London Borough of Havering
Romford
RM1 3BD
UK
Person cyswllt: Maria Faheem
E-bost: Maria.Faheem@havering.gov.uk
NUTS: UKI52
Cyfeiriad(au) rhyngrwyd
Prif gyfeiriad: www.havering.gov.uk
I.4) Y math o awdurdod contractio
Awdurdod rhanbarthol neu leol
I.5) Prif weithgaredd
Gwasanaethau cyhoeddus cyffredinol
Adran II: Gwrthrych
II.1) Cwmpas y caffaeliad
II.1.1) Teitl
Havering Estate Regeneration Partner – Property/Asset JV Company
II.1.2) Prif god CPV
45211340
II.1.3) Y math o gontract
Gwaith
II.1.4) Disgrifiad byr
LB of Havering (‘the Council’) entered into a contract for up to 30 years for a partner to form a long-term corporate joint venture (‘JV’) property vehicle to secure investment and expertise to deliver Havering’s housing led regeneration strategy, entered into 27 April 2018 (‘the Contract’). The opportunity was advertised in OJEU (2017/S 094-185114) and procured under the Concession Contracts Regulations 2016. Further details of the original Contract are in that OJEU Notice. The Contract includes a Members’ Agreement (MA) and Development Agreement (DA) with the JV LLP and other ancillary documents.
The Council has made additional funding available, refreshed the JV’s business plan and modified the DA. Further information can be found in the Council’s supplement document, at the web address in section II.2.4) below.
The information in the supplement document should be read in conjunction with this notice and both documents should be considered as a whole.
II.1.5) Cyfanswm gwerth amcangyfrifedig
Gwerth heb gynnwys TAW: 1 177 000 000.00 GBP
II.1.6) Gwybodaeth am lotiau
Mae’r contract hwn wedi’i rannu’n lotiau:
Na
II.1.7) Cyfanswm gwerth y caffaeliad
Gwerth heb gynnwys TAW: 1 177 000 000.00 GBP
II.2) Disgrifiad
II.2.2) Cod(au) CPV ychwanegol
45112700
45112710
45112711
45211300
45211341
45211350
45211360
45212000
45213100
45213112
45213150
45223300
65300000
70000000
70110000
70111000
70121100
70331000
70332200
71000000
71200000
71222000
71313400
71313420
71314200
71314300
71315200
71315300
71410000
71420000
71500000
71520000
71521000
73220000
79410000
79412000
79418000
90712100
45111000
II.2.3) Man cyflawni
Cod NUTS:
UKI52
Prif safle neu fan cyflawni:
The London Borough of Havering.
II.2.4) Disgrifiad o’r caffaeliad
Further info is at https://www.havering.gov.uk/downloads/download/876/veat_notice_supplement_documents
The Council has:
1) Made additional GBP 58.3 million equity funding available to JV. Also, refreshed JV business plan (BP) to include Council forward funding of GBP 45.4 million for phase 1 (in the light of additional 53 affordable housing units and reduction of open market units from 1085 to 934, changes to design and other factors);
2) Refreshed JV BP to remove Delta estate;
3) Refreshed JV BP to include addition of further sites;
4) Amended DA to bring forward timing of demolition of Waterloo Estate and Council providing additional GBP 7.8 million financing in place of debt funding (some changes to be made by variation to the DA and a new supplemental dev agreement with JV).
II.2.7) Hyd y contract, y cytundeb fframwaith, y system brynu ddynamig neu’r consesiwn
Hyd mewn misoedd: 360
II.2.13) Gwybodaeth am Gronfeydd yr Undeb Ewropeaidd
Mae'r broses gaffael yn gysylltiedig â phrosiect a/neu raglen a ariennir gan gronfeydd yr Undeb Ewropeaidd:
Na
II.2.14) Gwybodaeth ychwanegol
Est value in II.1.7) and V.2.4) is projected value of modified contract.
Please note, the duration field takes into account the fact that the concession started 11 December 2020.
Section IV: Gweithdrefn
IV.1) Disgrifiad
IV.1.1) Y math o weithdrefn
Y weithdrefn ddyfarnu heb gyhoeddi hysbysiad consesiwn ymlaen llaw yn yr achosion a restrir isod (llenwch Atodiad D4)
Cyfiawnhau'r weithdrefn ddyfarnu a ddewiswyd:
Mae’r caffaeliad y tu allan i gwmpas cymhwysiad y gyfarwyddeb
Esboniad
Please explain in a clear and comprehensive manner why the award of the contract without prior publication in the Official Journal of the European Union is lawful, by stating the relevant facts and, as appropriate, the conclusions of law in accordance with the directive:
Assessed individually and cumulatively, items 1–5 (as referred to in II.2.4) are all within the scope of the original OJEU/procurement and would not have affected the outcome (‘Procurement Outcome’).
The Council additionally/alternatively relies on Reg. 43(1)(a) (clear, precise, unequivocal review clauses), (c) (unforseeability), (e) (non substantial amendments — i.e. there is no material change in character of the contract, no considerable extension of scope, no distortion of competition and no change in the economic balance in favour of the contractor) and also Reg. 31(6)(b)(ii) as further described below:
The forward funding described in Change 1 and also Changes 2 and 3 are part of the annual business plan refresh, are within procurement scope and do not result in a change to the contract.
1) Re. additional equity funding: there is no increase in the Council’s peak net investment, no impact on the risk profile and no change in the economic balance. No change to the contract.
Re. forward funding: this is required due to a stagnant housing market eroding land value (impacting viability), build cost inflation, design enhancements, reduction in private sale cross subsidy and more affordable and family sized housing. These features would have applied to all bidders and the Council considers the Procurement Outcome would not have been impacted. Further, schedule 8, para 1.3 included scope to adjust Low Cost Unit Sum pursuant to VFM Standard and Code of Practice of Homes and Communities Agency;
2) Re. removal of the delta estate from current programme; this is a development phasing detail as no commitment was made to developing out the delta estate at this point in time, it was not tested as a sample scheme during the procurement process. Neither bidding behaviour nor Procurement Outcome would have been impacted;
3) Re. additional sites, these were within the OJEU notice scope and are similar to the sample sites tested as part of the procurement. Their delivery is consistent with financial and technical commitments in the tender to apply to subsequent schemes. The addition of further sites was transparently set out in the procurement documentation, is subject to an agreed mechanism and was incorporated into the evaluation questions. The Council alternatively relies on Reg 43(1)(a) (clear, precise, unequivocal review clauses).
IV.1.8) Gwybodaeth am Gytundeb Caffael y Llywodraeth (GPA)
The procurement is covered by the Government Procurement Agreement:
Ydy
IV.2) Gwybodaeth weinyddol
IV.2.1) Cyhoeddiad blaenorol mewn perthynas â’r weithdrefn hon
Rhif yr hysbysiad yn OJ S:
2017/S 094-185114
Section V: Dyfarnu contract
Teitl: Havering Estate Regeneration Partner – Property/Asset JV Company
Dyfernir contract/lot:
Ydy
V.2 Dyfarnu contract
V.2.1) Y dyddiad y daeth y contract i ben
11/12/2020
V.2.2) Gwybodaeth am dendrau
Nifer y tendrau a ddaeth i law: 1
Dyfarnwyd y contract i gr?p o weithredwyr economaidd:
Na
V.2.3) Enw a chyfeiriad y contractwr
Wates construction Ltd
Leatherhead
UK
NUTS: UKJ2
BBaCh yw’r contractwr:
Na
V.2.4) Gwybodaeth am werth y consesiwn a’r prif delerau cyllido (heb gynnwys TAW)
Cyfanswm gwerth y consesiwn/lot: 1 177 000 000.00 GBP
Section VI: Gwybodaeth ategol
VI.4) Gweithdrefnau adolygu
VI.4.1) Corff adolygu
The high court of justice
London
UK
VI.4.3) Gweithdrefn adolygu
Gwybodaeth fanwl gywir am y terfyn(au) amser ar gyfer gweithdrefnau adolygu:
In accordance with Regulation 49-64 (Applications to the Court) of the Concession Contracts Regulations 2016 (‘CCR’).
Cont from Annex D4 (expl. for type of procedure) (Section IV.1.1.):
4) OJEU notice contained demolition CPV and DA included demolition obligations. Council considered that bringing forward demolition and GBP 7.8 million financing would not impact on Proc outcome and was needed to expedite delivery and avoid additional costs. A change was made to DA and a new supplemental DA entered into re. this item alone. The procurement of an alternative contractor would have legal and financial ramifications for Council, would stall the 12 Site Regeneration Programme and would not be a reasonable alternative. The Council therefore further relied on Reg 31(6)(b)(ii);
5) Re. purchase of units and payment for NNP, Council also relied on: Reg 43(1)(c) - both changes were a reasonable and proportionate response to Covid (and needed to ensure the dev remains viable in current uncertain housing market). As per PPN01/20, changes are limited. The changes do not alter overall nature nor exceed original value by more than 50 %; Reg 43(1)(e) - NNP represents under 6 % of expected unit outputs;
Re. build contract sum, the Council accepted the risk of cost overruns, but any change was not substantial and surveys provide assurance on this. No impact on Proc Outcome; Reg 43(1)(a) – contract stated price to be paid on Practical Completion but envisaged a change could be made if provided in BP or agreed between parties.
6) The DA links 3 Sites (Napier New Plymouth, Serena Sunrise and Waterloo Phase 1) into Stage 1 and requires that the pre-conditions be satisfied in relation to all 3 sites and that the sites be drawn down together for development. The DA has been varied to allow each of the Stage 1 Sites to be drawn down separately (in an order to be agreed between the parties) rather than all of Stage 1 having to be drawn down together. No impact on Proc Outcome Reg. 43(1)(e) in terms of the requirement to build out all 3 sites remaining in place and it is still proposed that they will be developed in close proximity in programme.
Further information can be found in the Council’s supplement document.
VI.5) Dyddiad anfon yr hysbysiad hwn
13/04/2021