Skip to main content

Rydym wedi cadw rhai ffeiliau o'r enw cwcis ar eich dyfais. Y cwcis hyn yw:

  • Hanfodol ar gyfer y safle i weithio
  • Helpu i wella ein gwefan drwy gasglu ac adrodd gwybodaeth am sut rydych chi'n ei defnyddio

Hoffem hefyd arbed rhai cwcis i helpu i deilwra cyfathrebu.

BETA
Rydych yn edrych ar fersiwn wedi'i ddiweddaru o'r gwasanaeth hwn - bydd eich adborth yn ein helpu i'w wella.

Dyfarnu Contract

Framework Agreements relating to provision of maintenance services by Original Equipment Manufacturer

  • Cyhoeddwyd gyntaf: 16 Rhagfyr 2022
  • Wedi'i addasu ddiwethaf: 16 Rhagfyr 2022

Nid yw'r prynwr yn defnyddio'r wefan hon i weinyddu'r hysbysiad.

I gofnodi eich diddordeb neu gael gwybodaeth neu ddogfennau ychwanegol, darllenwch y cyfarwyddiadau yn Nhestun Llawn yr Hysbysiad. (NODER: Nid oes angen ymateb i Hysbysiadau Dyfarnu Contractau a Hysbysiadau Gwybodaeth Ymlaen Llaw fel arfer)

Cynnwys

Crynodeb

OCID:
ocds-h6vhtk-038dbe
Cyhoeddwyd gan:
National Grid Electricity Transmission plc
ID Awudurdod:
AA78559
Dyddiad cyhoeddi:
16 Rhagfyr 2022
Dyddiad Cau:
-
Math o hysbysiad:
Dyfarnu Contract
Mae ganddo ddogfennau:
Nac Ydi
Wedi SPD:
Nac Ydi
Mae ganddo gynllun lleihau carbon:
AMH

Crynodeb

National Grid has entered into framework agreements with UK Grid Solutions, Siemens Energy Limited and Hitachi Energy Limited to enable any member of the National Grid Group to procure the design, engineering, manufacture, supply, project management, construction, erection and commissioning in respect of the OEMs' equipment. This shall include the support and/or delivery of substation interventions on the OEMs' equipment and any other business related requirements it may request from time to time and the OEMs have agreed to carry out these works and services on a non-exclusive basis upon any member of the National Grid Group placing a Call Off Order in accordance with the Framework Agreements.

The awards have been made without prior call for competition in accordance with Regulation 50(1)(c)(iii) on account of the fact that the services can only be carried out by the OEMs due to protection of exclusive rights (IP rights) and no reasonable alternative exists as National Grid does not own the IP rights to commission services from third parties. National Grid cannot simply replace the equipment rather than repair it and the scope of the frameworks is the minimum necessary to protect the OEMs' IP rights.

The frameworks each have an initial five-year term which may be extended by one of more additional period of 1-year up to a maximum of 3 additional years following the end of the initial term.

Please note that the total value figure included in Sections II.1.7 and V.2.4 is an estimate only in respect of the total three frameworks and the estimated value of the frameworks is expected to be a range of £38,000,000 - £45,000,000 per framework over the full potential term of the frameworks (including extensions). Please note, however, that the framework is intended to cover all potential services required over the full course of each framework and this figure is National Grid's best estimate based on current information and is not intended to be a cap or maximum figure which cannot be exceeded.

Testun llawn y rhybydd

Hysbysiad dyfarnu contract – cyfleustodau

Adran I: Endid contractio

I.1) Enw a chyfeiriad

NATIONAL GRID ELECTRICITY TRANSMISSION PLC

National Grid UK Limited

1 - 3 Strand

LONDON

WC2N5EH

UK

Ffôn: +44 7976989186

E-bost: box.GP.UKBuyerNGET@nationalgrid.com

NUTS: UK

Cyfeiriad(au) rhyngrwyd

Prif gyfeiriad: www.nationalgrid.com

I.6) Prif weithgaredd

Trydan

Adran II: Gwrthrych

II.1) Cwmpas y caffaeliad

II.1.1) Teitl

Framework Agreements relating to provision of maintenance services by Original Equipment Manufacturer

II.1.2) Prif god CPV

31682540

 

II.1.3) Y math o gontract

Cyflenwadau

II.1.4) Disgrifiad byr

Framework Agreements awarded pursuant to Regulation 50(1)(c)(iii) UCR 2016 to Original Equipment Manufacturers ("OEMs") in respect of support and/or delivery of substation interventions to the OEMs' equipment. The services can only be carried out by the OEMs due to protection of exclusive rights (IP rights) and no reasonable alternative exists as National Grid does not own the IP rights to commission services from third parties.

II.1.6) Gwybodaeth am lotiau

Mae’r contract hwn wedi’i rannu’n lotiau: Na

II.1.7) Cyfanswm gwerth y caffaeliad

Cynnig isaf:   / Y cynnig uchaf:  

II.2) Disgrifiad

II.2.2) Cod(au) CPV ychwanegol

50000000

II.2.3) Man cyflawni

Cod NUTS:

UK

II.2.4) Disgrifiad o’r caffaeliad

National Grid has entered into framework agreements with UK Grid Solutions, Siemens Energy Limited and Hitachi Energy Limited to enable any member of the National Grid Group to procure the design, engineering, manufacture, supply, project management, construction, erection and commissioning in respect of the OEMs' equipment. This shall include the support and/or delivery of substation interventions on the OEMs' equipment and any other business related requirements it may request from time to time and the OEMs have agreed to carry out these works and services on a non-exclusive basis upon any member of the National Grid Group placing a Call Off Order in accordance with the Framework Agreements.

The awards have been made without prior call for competition in accordance with Regulation 50(1)(c)(iii) on account of the fact that the services can only be carried out by the OEMs due to protection of exclusive rights (IP rights) and no reasonable alternative exists as National Grid does not own the IP rights to commission services from third parties. National Grid cannot simply replace the equipment rather than repair it and the scope of the frameworks is the minimum necessary to protect the OEMs' IP rights.

The frameworks each have an initial five-year term which may be extended by one of more additional period of 1-year up to a maximum of 3 additional years following the end of the initial term.

Please note that the total value figure included in Sections II.1.7 and V.2.4 is an estimate only in respect of the total three frameworks and the estimated value of the frameworks is expected to be a range of £38,000,000 - £45,000,000 per framework over the full potential term of the frameworks (including extensions). Please note, however, that the framework is intended to cover all potential services required over the full course of each framework and this figure is National Grid's best estimate based on current information and is not intended to be a cap or maximum figure which cannot be exceeded.

II.2.11) Gwybodaeth am opsiynau

Opsiynau: Ydy

Disgrifiad o’r opsiynau:

1.1 The Term may be extended by one or more additional period of 1 (one) year (each being an "Extension Period") at the sole option of the Framework Client (but not at the sole option of any other National Grid Group member) up to a maximum of 3 (three) additional years by service of a written notice on the Contractor provided that such a notice of extension shall be given by the Framework Client no later than 3 (three) months prior to the end of the initial 5 (five) year Term (or 3 (three) months prior to the expiry of each such Extension Period as the case may be). In the event of such Extension Period the same terms of this Agreement shall apply.

II.2.13) Gwybodaeth am Gronfeydd yr Undeb Ewropeaidd

Mae'r broses gaffael yn gysylltiedig â phrosiect a/neu raglen a ariennir gan gronfeydd yr Undeb Ewropeaidd: Na

Section IV: Gweithdrefn

IV.1) Disgrifiad

IV.1.1) Y math o weithdrefn

Dyfarnu contract heb gyhoeddi galwad am gystadleuaeth yng Nghyfnodolyn Swyddogol yr Undeb Ewropeaidd ymlaen llaw

Cyfiawnhau'r weithdrefn ddyfarnu a ddewiswyd:

Dim ond am y rheswm canlynol y gall gweithredwr economaidd penodol ddarparu'r gwaith, y cyflenwadau neu'r gwasanaethau: diogelu hawliau unigryw, gan gynnwys hawliau eiddo deallusol

Esboniad

The awards have been made without prior call for competition in accordance with Regulation 50(1)(c)(iii) on account of the fact that the services can only be carried out by the OEMs due to protection of exclusive rights (IP rights) and no reasonable alternative exists as National Grid does not own the IP rights to commission services from third parties. National Grid cannot simply replace the equipment rather than repair it and the scope of the frameworks is the minimum necessary to protect the OEMs' IP rights.

IV.1.3) Gwybodaeth am gytundeb fframwaith neu system brynu ddynamig

Mae'r broses gaffael yn golygu sefydlu cytundeb fframwaith gydag un gweithredwr.

IV.1.8) Gwybodaeth am Gytundeb Caffael y Llywodraeth (GPA)

The procurement is covered by the Government Procurement Agreement: Na

Section V: Dyfarnu contract

Dyfernir contract/lot: Ydy

V.2 Dyfarnu contract

V.2.1) Y dyddiad y daeth y contract i ben

13/12/2022

V.2.2) Gwybodaeth am dendrau

Dyfarnwyd y contract i gr?p o weithredwyr economaidd: Na

V.2.5) Gwybodaeth am is-gontractio

Section VI: Gwybodaeth ategol

VI.4) Gweithdrefnau adolygu

VI.4.1) Corff adolygu

Royal Courts of Justice

Strand

London

WC2A 2LL

UK

VI.5) Dyddiad anfon yr hysbysiad hwn

15/12/2022

Codio

Categorïau nwyddau

ID Teitl Prif gategori
31682540 Cyfarpar is-orsaf Cyflenwadau trydan
50000000 Gwasanaethau atgyweirio a chynnal a chadw Gwasanaethau eraill

Lleoliadau Dosbarthu

ID Disgrifiad
100 DU - I gyd

Cyfyngiadau Rhanbarthol ar y Rhybuddion

Mae’r prynwr wedi cyfyngu’r rhybuddion ar gyfer yr hysbysiad hwn i gyflenwyr yn y rhanbarthau canlynol.

ID Disgrifiad
Nid oes cyfyngiadau ar y rhybuddion ar gyfer yr hysbysiad hwn.

Ynglŷn â'r prynwr

Prif gyswllt:
box.GP.UKBuyerNGET@nationalgrid.com
Cyswllt gweinyddol:
N/a
Cyswllt technegol:
N/a
Cyswllt arall:
N/a

Gwybodaeth bellach

Dyddiad Manylion
Nid oes unrhyw wybodaeth bellach wedi'i lanlwytho.

0800 222 9004

Mae'r llinellau ar agor rhwng 8:30am a 5pm o ddydd Llun i ddydd Gwener.

Rydym yn croesawu galwadau'n Gymraeg.

We welcome calls in Welsh.