Dyfarnu Contract

Midlands Rail Hub Alliance – Alliance Partners (Non-Signalling Disciplines)

  • Cyhoeddwyd gyntaf: 20 Rhagfyr 2025
  • Wedi'i addasu ddiwethaf: 20 Rhagfyr 2025
  • Fersiwn: N/A
  • Cofnodi Diddordeb

     

  • Efallai na fydd y ffeil hon yn gwbl hygyrch.

  •  

Eicon Gwybodaeth

Nid yw'r prynwr yn defnyddio'r wefan hon i weinyddu'r hysbysiad.

I gofnodi eich diddordeb neu gael gwybodaeth neu ddogfennau ychwanegol, darllenwch y cyfarwyddiadau yn Nhestun Llawn yr Hysbysiad. (NODER: Nid oes angen ymateb i Hysbysiadau Dyfarnu Contractau a Hysbysiadau Gwybodaeth Ymlaen Llaw fel arfer)

Cynnwys

Crynodeb

OCID:
Cyhoeddwyd gan:
Network Rail Infrastructure Ltd
ID Awudurdod:
AA73642
Dyddiad cyhoeddi:
20 Rhagfyr 2025
Dyddiad Cau:
-
Math o hysbysiad:
Dyfarnu Contract
Mae ganddo ddogfennau:
Nac Ydi
Wedi SPD:
Nac Ydi
Mae ganddo gynllun lleihau carbon:
AMH

Crynodeb

Network Rail is responsible for maintaining, developing and operating Great Britain's railway infrastructure. The Midlands Rail Hub (MRH) is a programme of works covering a series of multidisciplinary infrastructure interventions to be undertaken across the West, Central and East Midlands of the UK. MRH will deliver a number of additional services between central Birmingham and key regional cities and transport hubs.

The MRH programme will be delivered through an Alliance delivery model with Alliance members consisting of:

- Network Rail (having two roles – one as a member of the Alliance and the other as Client);

- Multi-Disciplinary Partner(s) (covering all disciplines except signalling, power and communication roles set out in the Alliance scope document) appointed pursuant to this Contract Award Notice; and

- A Signalling Partner (covering the signalling, power and communication roles set out in the Alliance scope document) appointed via a separate sourcing event.

Testun llawn y rhybydd

Hysbysiad dyfarnu contract – cyfleustodau

Adran I: Endid contractio

I.1) Enw a chyfeiriad

Network Rail Infrastructure Ltd

Waterloo General Offices

London

SE1 8SW

UK

Person cyswllt: Louise Mackay

Ffôn: +44 1908781000

E-bost: Louise.Mackay@networkrail.co.uk

NUTS: UK

Cyfeiriad(au) rhyngrwyd

Prif gyfeiriad: https://www.networkrail.co.uk

I.6) Prif weithgaredd

Gwasanaethau rheilffyrdd

Adran II: Gwrthrych

II.1) Cwmpas y caffaeliad

II.1.1) Teitl

Midlands Rail Hub Alliance – Alliance Partners (Non-Signalling Disciplines)

II.1.2) Prif god CPV

45234100

 

II.1.3) Y math o gontract

Gwaith

II.1.4) Disgrifiad byr

Network Rail is responsible for maintaining, developing and operating Great Britain's railway infrastructure. The Midlands Rail Hub (MRH) is a programme of works covering a series of multidisciplinary infrastructure interventions to be undertaken across the West, Central and East Midlands of the UK. MRH will deliver a number of additional services between central Birmingham and key regional cities and transport hubs.

The MRH programme will be delivered through an Alliance delivery model with Alliance members consisting of:

- Network Rail (having two roles – one as a member of the Alliance and the other as Client);

- Multi-Disciplinary Partner(s) (covering all disciplines except signalling, power and communication roles set out in the Alliance scope document) appointed pursuant to this Contract Award Notice; and

- A Signalling Partner (covering the signalling, power and communication roles set out in the Alliance scope document) appointed via a separate sourcing event.

II.1.6) Gwybodaeth am lotiau

Mae’r contract hwn wedi’i rannu’n lotiau: Na

II.1.7) Cyfanswm gwerth y caffaeliad

Gwerth heb gynnwys TAW: 1 380 000 000.00 GBP

II.2) Disgrifiad

II.2.2) Cod(au) CPV ychwanegol

45000000

45100000

45111213

45200000

45210000

45213320

45213321

45221112

45221122

45221242

45232210

45234100

45234114

71321000

71322000

71332000

II.2.3) Man cyflawni

Cod NUTS:

UK

II.2.4) Disgrifiad o’r caffaeliad

The key objectives of MRH are to improve connectivity across the Midlands region; boost economic growth; maximise use of HS2 to London through interchange in Central Birmingham; improve access to jobs, leisure, healthcare, and education; optimise the utilisation of station capacity in central Birmingham; and make rail journeys more attractive and encourage modal shift to rail.

The scope of the Alliance includes, but is not limited to, the design and build of: new platforms and sidings; up to two new chords into Birmingham Moor Street; widening of existing viaduct; power supply upgrades; new freight loops; new overhead line equipment (OLE) and various signalling works including the re-modelling of existing layouts.

The MRH programme consists of multidisciplinary infrastructure interventions are split over three sections described as West, Central and East according to the additional train services that they enable. The scope is currently divided into eight interventions across the three sections: West & Central Midlands interventions at Snow Hill, King’s Norton to Barnt Green (and interventions at King’s Norton and Barnt Green) and Birmingham Bordesley to Moor Street are in the process of securing final funding approval and are intended to be the initial deliverables. Additional interventions are also in scope of MRH and may be delivered subject to funding decisions and design development including West & Central interventions at Worcester to Hereford and Stoke Works Junction and East Midlands interventions at Water Orton and Nuneaton to Wigston.

East interventions are at an earlier stage of design development and are intended to form part of a separate business case; these interventions are subject to future funding decisions. It is also envisaged that the West intervention of Worcester-Hereford will be delivered by the Alliance but does not form part of the initial deliverables and is dependent upon as yet uncommitted renewals in the Worcester area.

The total Alliance Anticipated Final Cost (AFC) excluding VAT is circa £1.1m--£1.5bn GBP.

The AFC is split between the initial deliverables and additional interventions as follows:

- Initial deliverables (predominantly interventions in West and Central) are circa:

- Multi-Disciplinary (non-signalling, power and communications): £700m-£800m GBP (excluding VAT)

- Signalling, power and communications; £150m-£250m GBP (excluding VAT)

- Additional interventions (predominantly East) are circa:

- Multi-Disciplinary (non-signalling power and communications: £250m-£350m GBP (excluding VAT);

- Signalling, power and communications; £50m-£100m GBP (excluding VAT)

These figures are indicative only.

Network Rail has appointed all Partners to the Alliance using a modified NR35 Alliance Contract (based on the NEC4 Alliance Contract). Network Rail and each of the Partners have signed one Alliance contract.

II.2.11) Gwybodaeth am opsiynau

Opsiynau: Na

II.2.13) Gwybodaeth am Gronfeydd yr Undeb Ewropeaidd

Mae'r broses gaffael yn gysylltiedig â phrosiect a/neu raglen a ariennir gan gronfeydd yr Undeb Ewropeaidd: Na

Section IV: Gweithdrefn

IV.1) Disgrifiad

IV.1.1) Y math o weithdrefn

negodi gyda galwad am gystadleuaeth

IV.1.8) Gwybodaeth am Gytundeb Caffael y Llywodraeth (GPA)

The procurement is covered by the Government Procurement Agreement: Ydy

IV.2) Gwybodaeth weinyddol

IV.2.1) Cyhoeddiad blaenorol mewn perthynas â’r weithdrefn hon

Rhif yr hysbysiad yn OJ S:

2024/S 000-006185

Section V: Dyfarnu contract

Rhif Contract: ecm_49994

Dyfernir contract/lot: Ydy

V.2 Dyfarnu contract

V.2.1) Y dyddiad y daeth y contract i ben

17/12/2025

V.2.2) Gwybodaeth am dendrau

Dyfarnwyd y contract i gr?p o weithredwyr economaidd: Ydy

V.2.3) Enw a chyfeiriad y contractwr

VolkerRail Limited

Hoddesdon

UK

NUTS: UK

BBaCh yw’r contractwr: Na

V.2.3) Enw a chyfeiriad y contractwr

Laing O'Rourke Delivery Limited

Dartford

UK

NUTS: UK

BBaCh yw’r contractwr: Na

V.2.3) Enw a chyfeiriad y contractwr

AtkinsRealis UK Limited

Epsom

UK

NUTS: UK

BBaCh yw’r contractwr: Na

V.2.4) Gwybodaeth am werth y contract/lot (heb gynnwys VAT)

Cyfanswm gwerth y contract/lot: 103 509 864.00 GBP

V.2.5) Gwybodaeth am is-gontractio

Section VI: Gwybodaeth ategol

VI.4) Gweithdrefnau adolygu

VI.4.1) Corff adolygu

High Court of England and Wales Royal Courts of Justice

Strand

London

WC1A 2LL

UK

VI.4.2) Corff sy’n gyfrifol am weithdrefnau cyfryngu

High Court of England and Wales Royal Courts of Justice

Strand

London

W1CA 2LL

UK

VI.5) Dyddiad anfon yr hysbysiad hwn

19/12/2025

Codio

Categorïau nwyddau

ID Teitl Prif gategori
45232210 Adeiladu llinellau uwchben Gwaith ategol ar gyfer piblinellau a cheblau
45000000 Gwaith adeiladu Adeiladu ac Eiddo Tiriog
45210000 Gwaith adeiladu adeiladau Gwaith ar gyfer gwaith adeiladau cyflawn neu rannol a gwaith peirianneg sifil
45213320 Gwaith adeiladu ar gyfer adeiladau sy’n gysylltiedig â thrafnidiaeth rheilffyrdd Gwaith adeiladu ar gyfer adeiladau masnachol, warysau ac adeiladau diwydiannol, adeiladau sy’n gysylltiedig â thrafnidiaeth
45234114 Gwaith adeiladu argloddiau rheilffordd Gwaith adeiladu ar gyfer rheilffyrdd a systemau cludiant ceblau
45213321 Gwaith adeiladu gorsafoedd trenau Gwaith adeiladu ar gyfer adeiladau masnachol, warysau ac adeiladau diwydiannol, adeiladau sy’n gysylltiedig â thrafnidiaeth
45221112 Gwaith adeiladu pontydd rheilffordd Gwaith adeiladu ar gyfer pontydd a thwneli, siafftiau ac isffyrdd
45234100 Gwaith adeiladu rheilffyrdd Gwaith adeiladu ar gyfer rheilffyrdd a systemau cludiant ceblau
45221122 Gwaith adeiladu traphontydd rheilffordd Gwaith adeiladu ar gyfer pontydd a thwneli, siafftiau ac isffyrdd
45221242 Gwaith adeiladu twneli rheilffordd Gwaith adeiladu ar gyfer pontydd a thwneli, siafftiau ac isffyrdd
45200000 Gwaith ar gyfer gwaith adeiladau cyflawn neu rannol a gwaith peirianneg sifil Gwaith adeiladu
45111213 Gwaith clirio safleoedd Gwaith dymchwel, paratoi a chlirio safleoedd
45100000 Gwaith paratoi safleoedd Gwaith adeiladu
71322000 Gwasanaethau dylunio peirianneg ar gyfer adeiladu gwaith peirianneg sifil Gwasanaethau dylunio peirianneg
71321000 Gwasanaethau dylunio peirianneg ar gyfer gwaith gosod mecanyddol a thrydanol ar gyfer adeiladau Gwasanaethau dylunio peirianneg
71332000 Gwasanaethau peirianneg geotechnegol Gwasanaethau peirianneg amrywiol

Lleoliadau Dosbarthu

ID Disgrifiad
100 DU - I gyd

Cyfyngiadau Rhanbarthol ar y Rhybuddion

Mae’r prynwr wedi cyfyngu’r rhybuddion ar gyfer yr hysbysiad hwn i gyflenwyr yn y rhanbarthau canlynol.

ID Disgrifiad
Nid oes cyfyngiadau ar y rhybuddion ar gyfer yr hysbysiad hwn.

Ynglŷn â'r prynwr

Prif gyswllt:
Louise.Mackay@networkrail.co.uk
Cyswllt gweinyddol:
N/a
Cyswllt technegol:
N/a
Cyswllt arall:
N/a

Gwybodaeth bellach

Dyddiad Manylion
Nid oes unrhyw wybodaeth bellach wedi'i lanlwytho.