Hysbysiad dyfarnu contract
Canlyniadau'r weithdrefn gaffael
Adran I: 
        Endid 
       contractio 
I.1) Enw a chyfeiriad
  Wiltshire Council
  Wiltshire Council, County Hall, Bythesea Road
  Trowbridge
  BA14 8JN
  UK
  
            Person cyswllt: Mr Dave Gillett
  
            Ffôn: +44 1255713371
  
            E-bost: david.gillett@wiltshire.gov.uk
  
            NUTS: UKK15
  Cyfeiriad(au) rhyngrwyd
  
              Prif gyfeiriad: http://www.wiltshire.gov.uk/
  
              Cyfeiriad proffil y prynwr: http://www.wiltshire.gov.uk/
 
I.4) Y math o awdurdod contractio
Awdurdod rhanbarthol neu leol
I.5) Prif weithgaredd
Gwasanaethau cyhoeddus cyffredinol
Adran II: Gwrthrych
II.1) Cwmpas y caffaeliad
  II.1.1) Teitl
  HE0914 A350 Chippenham Duelling Scheme April 2023
  
            Cyfeirnod: DN637737
  II.1.2) Prif god CPV
  45233100
 
  II.1.3) Y math o gontract
  Gwaith
  II.1.4) Disgrifiad byr
  he A350 is one of the most important routes in Wiltshire. It is a primary north-south route with regional significance connecting the south coast with the M4 and onwards to Bristol and the Midlands. In Wiltshire it passes around the principal settlements of Chippenham and Trowbridge via the town of Melksham and on to Westbury and Warminster.
  It has been a longstanding priority to improve north-south connectivity along the A350, and Wiltshire Council has been progressively bringing forward the dualling of the A350 Chippenham bypass.
  Over recent years three major capital schemes (Phases 1, 2 and 3) have been brought forward to improve capacity and safety on the route, largely funded through successful Department for Transport (DfT) and/or Local Enterprise Partnerships (LEP) funding bids.
  Most recently, an Outline Business Case (OBC) bid was made to DfT for funding to bring forward a scheme to complete the dualling of the A350 bypass at Chippenham.
  In the spending review in October 2021 the government announced that it would allocate funds for a scheme to dual the remaining single carriageway sections of the A350 route round Chippenham. The project was also included within the list of forthcoming infrastructure projects as part of The Growth Plan 2022 published in September 2022.
  Wiltshire Council and its consultants Atkins are now pressing forward to complete the design of the remaining Phases 4 and 5 of the scheme, and preparing the Full Business Case (FBC). Subject to the FBC being approved by the DfT, it is anticipated that construction works will be undertaken during 2024 and 2025.
  The scheme is likely to include for the following key elements
  Phase 4 dualling: widening the A350 over a total distance of some 1.5km to dual 2-lane between Chequers roundabout and Lackham roundabout. The dualling would take place within the existing wide highway verge to the west of the current carriageway.
  Phase 5 dualling: widening the A350 over a total distance of some 1.75km to dual 2-lane between Cepen Park South roundabout and Bumpers Farm roundabout. Again, the dualling would take place within the existing wide highway verge to the west of the current carriageway. When implemented with Phase 4, this would extend the dualling to cover the full stretch of the A350 Chippenham Bypass.
  Bumpers Farm Roundabout capacity enhancements: increasing the circulatory from 2 lanes to 3; signalising 4 approach arms; increasing approach arms from A350 (S), A420 (W), A350 (N) and A420 (E) to 3 lanes; and dualling the exits onto the A420 (E) and A420 (W) and
  Lackham roundabout capacity enhancements: dualling the exit to the A350 north as part of the phase 4 works.
  The works will be designed and built-in accordance with current standards and guidelines and will include for all key aspects of highway construction – earthworks, carriageway, footways, drainage, street lighting, signage, statutory authority (gas, water electric etc) service diversions and provision, and hard and soft landscaping works.
  The works will be contained within the existing highway boundary extents and there should be no requirement for additional land. The existing bridges along this route were constructed to accommodate the additional carriageways without needing further major works, and as such there are no major structural works anticipated.
  The A350 route will need to remain in operation throughout the works, and as such careful traffic management considerations and phasing, particularly in connection with the Bumpers Farm Roundabout enhancements, will be required. There will be a desire to minimise impacts on traffic flows during the works and ensure that the scheme is undertaken with suitable and appropriate levels of public engagement and liaison.
  II.1.6) Gwybodaeth am lotiau
  
            Mae’r contract hwn wedi’i rannu’n lotiau:
            
        Na
      
  II.1.7) Cyfanswm gwerth y caffaeliad
  
                Gwerth heb gynnwys TAW: 21 191 000 000.00 GBP
 
II.2) Disgrifiad
  
    II.2.2) Cod(au) CPV ychwanegol
    45233120
    45233121
    45233122
    45233128
    45233221
    45233224
    45233124
    45233210
    45233280
    45233290
    45233130
    45233293
    45233300
    45233310
    II.2.3) Man cyflawni
    Cod NUTS:
    UKK15
    II.2.4) Disgrifiad o’r caffaeliad
    he A350 is one of the most important routes in Wiltshire. It is a primary north-south route with regional significance connecting the south coast with the M4 and onwards to Bristol and the Midlands. In Wiltshire it passes around the principal settlements of Chippenham and Trowbridge via the town of Melksham and on to Westbury and Warminster.
    It has been a longstanding priority to improve north-south connectivity along the A350, and Wiltshire Council has been progressively bringing forward the dualling of the A350 Chippenham bypass.
    Over recent years three major capital schemes (Phases 1, 2 and 3) have been brought forward to improve capacity and safety on the route, largely funded through successful Department for Transport (DfT) and/or Local Enterprise Partnerships (LEP) funding bids.
    Most recently, an Outline Business Case (OBC) bid was made to DfT for funding to bring forward a scheme to complete the dualling of the A350 bypass at Chippenham.
    In the spending review in October 2021 the government announced that it would allocate funds for a scheme to dual the remaining single carriageway sections of the A350 route round Chippenham. The project was also included within the list of forthcoming infrastructure projects as part of The Growth Plan 2022 published in September 2022.
    Wiltshire Council and its consultants Atkins are now pressing forward to complete the design of the remaining Phases 4 and 5 of the scheme, and preparing the Full Business Case (FBC). Subject to the FBC being approved by the DfT, it is anticipated that construction works will be undertaken during 2024 and 2025.
    The scheme is likely to include for the following key elements
    Phase 4 dualling: widening the A350 over a total distance of some 1.5km to dual 2-lane between Chequers roundabout and Lackham roundabout. The dualling would take place within the existing wide highway verge to the west of the current carriageway.
    Phase 5 dualling: widening the A350 over a total distance of some 1.75km to dual 2-lane between Cepen Park South roundabout and Bumpers Farm roundabout. Again, the dualling would take place within the existing wide highway verge to the west of the current carriageway. When implemented with Phase 4, this would extend the dualling to cover the full stretch of the A350 Chippenham Bypass.
    Bumpers Farm Roundabout capacity enhancements: increasing the circulatory from 2 lanes to 3; signalising 4 approach arms; increasing approach arms from A350 (S), A420 (W), A350 (N) and A420 (E) to 3 lanes; and dualling the exits onto the A420 (E) and A420 (W) and
    Lackham roundabout capacity enhancements: dualling the exit to the A350 north as part of the phase 4 works.
    The works will be designed and built-in accordance with current standards and guidelines and will include for all key aspects of highway construction – earthworks, carriageway, footways, drainage, street lighting, signage, statutory authority (gas, water electric etc) service diversions and provision, and hard and soft landscaping works.
    The works will be contained within the existing highway boundary extents and there should be no requirement for additional land. The existing bridges along this route were constructed to accommodate the additional carriageways without needing further major works, and as such there are no major structural works anticipated.
    The A350 route will need to remain in operation throughout the works, and as such careful traffic management considerations and phasing, particularly in connection with the Bumpers Farm Roundabout enhancements, will be required. There will be a desire to minimise impacts on traffic flows during the works and ensure that the scheme is undertaken with suitable and appropriate levels of public engagement and liaison.
    II.2.5) Meini prawf dyfarnu
    
                    Maes prawf ansawdd: Quality
                    / Pwysoliad: 40
    
                    Price
                    
                      / Pwysoliad: 
                      60
    II.2.11) Gwybodaeth am opsiynau
    
            Opsiynau:
            
              Na
            
    II.2.13) Gwybodaeth am Gronfeydd yr Undeb Ewropeaidd
    
            Mae'r broses gaffael yn gysylltiedig â phrosiect a/neu raglen a ariennir gan gronfeydd yr Undeb Ewropeaidd:
            
              Na
            
   
 
Section IV: Gweithdrefn
IV.1) Disgrifiad
  IV.1.1) Y math o weithdrefn
  
                        Gweithdrefn gyfyngedig
                        
  IV.1.8) Gwybodaeth am Gytundeb Caffael y Llywodraeth (GPA)
  
                The procurement is covered by the Government Procurement Agreement:
                
        Ydy
      
 
IV.2) Gwybodaeth weinyddol
  IV.2.1) Cyhoeddiad blaenorol mewn perthynas â’r weithdrefn hon
  Rhif yr hysbysiad yn OJ S:
  2023/S 000-012215
 
Section V: Dyfarnu contract
          Rhif Contract: HE0914 A350
          Teitl: HE0914 A350 Chippenham Duelling Scheme April 2023
        Dyfernir contract/lot:
        
        Ydy
      
V.2 Dyfarnu contract
V.2.1) Y dyddiad y daeth y contract i ben
29/04/2025
V.2.2) Gwybodaeth am dendrau
                Nifer y tendrau a ddaeth i law: 13
                Nifer y tendrau a ddaeth i law gan BBaChau: 5
                Nifer y tendrau a dderbyniwyd gan dendrwyr o Aelod-wladwriaethau yr UE: 13
                Nifer y tendrau a dderbyniwyd gan dendrwyr o Aelod-wladwriaethau nad ydynt yn aelodau o'r UE: 0
                Nifer y tendrau a ddaeth i law drwy ddulliau electronig: 13
              Dyfarnwyd y contract i gr?p o weithredwyr economaidd:
              
        Na
      
V.2.3) Enw a chyfeiriad y contractwr
  MJ Church (Plant) Ltd
  Saltersford Lane
  Chippenham
  SN14 0RN
  UK
  
            NUTS: UKK15
  BBaCh yw’r contractwr:
        Ydy
      
 
                V.2.4) Gwybodaeth am werth y contract/lot  (heb gynnwys VAT)
              
                    Cyfanswm gwerth y contract/lot: 21 191 000 000.00 GBP
V.2.5) Gwybodaeth am is-gontractio
Section VI: Gwybodaeth ategol
VI.4) Gweithdrefnau adolygu
  VI.4.1) Corff adolygu
  
    High Court of England and Wales
    The Royal Court of Justice, Strand
    London
    WC2A 2LL
    UK
   
 
VI.5) Dyddiad anfon yr hysbysiad hwn
30/04/2025