Hysbysiad dyfarnu contract – cyfleustodau
Adran I:
Endid
contractio
I.1) Enw a chyfeiriad
HS2
High Speed Two (HS2) Limited, Two Snowhill, Snow Hill Queensway
Birmingham
B4 6GA
UK
E-bost: scc@hs2.org.uk
NUTS: UK
Cyfeiriad(au) rhyngrwyd
Prif gyfeiriad: https://www.hs2.org.uk/
I.6) Prif weithgaredd
Gwasanaethau rheilffyrdd
Adran II: Gwrthrych
II.1) Cwmpas y caffaeliad
II.1.1) Teitl
High Speed Two (HS2) Limited, Phase Two - Framework Agreement for Phase Two Route Wide Ground Investigation
II.1.2) Prif god CPV
45111250
II.1.3) Y math o gontract
Gwaith
II.1.4) Disgrifiad byr
High Speed Two (HS2) Limited has awarded a Framework Agreement for the Phase Two Route Wide Ground Investigation (separated into 2 Lots). Lot 1 for the management and co-ordination of the packaging of GI works as well as the planning and implementation of GI site enabling works (Ground Investigation Partner (GIP)). Lot 2 for the acquisition of geotechnical, hydrogeological and geo-environmental data through surveys, the excavation and detailed logging of exploratory holes, and in-situ and laboratory testing, culminating in the production of factual reports (Ground Investigation Contractor (GIC)), some land of which will be in areas of historic mining. Ground Investigations may also be required and called off under the Framework Agreement as optional scope at other HS2 sites or by Contracting Bodies other than HS2 Ltd (see VI.3 below).
II.1.6) Gwybodaeth am lotiau
Mae’r contract hwn wedi’i rannu’n lotiau:
Ydy
II.1.7) Cyfanswm gwerth y caffaeliad
Gwerth heb gynnwys TAW: 300 000 000.00 GBP
II.2) Disgrifiad
Rhif y Lot 1
II.2.1) Teitl
Lot 1- Ground Investigation Partner (GIP)
II.2.2) Cod(au) CPV ychwanegol
71332000
71351500
71355000
71510000
71541000
71900000
73111000
79311200
79311300
II.2.3) Man cyflawni
Cod NUTS:
UK
II.2.4) Disgrifiad o’r caffaeliad
Lot 1 is for the appointment of a single Ground Investigation Partner (GIP) to undertake the management and co-ordination of the packaging of GI works as well as the planning and implementation of GI site enabling works across the Phase Two route. The Framework Agreement has a duration of 8 years with works/services anticipated to be undertaken over a four-year period during that term although works/services may extend over a longer period and further HS2 Ltd retains the option to extend the Framework Agreement for a further two years in the event of delays to the GI programme (see II.2.11) (Information about options) for further information)). Further works may also be required and called off under the Framework Agreement as optional scope at other HS2 sites or by Contracting Bodies other than HS2 Ltd (see VI.3 below).
II.2.5) Meini prawf dyfarnu
Maes prawf ansawdd: Qualification Requirements
/ Pwysoliad: pass/fail
Maes prawf ansawdd: Technical Requirements
/ Pwysoliad: pass/fail
Maen prawf cost: Value for money requirements
/ Pwysoliad: pass/fail
II.2.11) Gwybodaeth am opsiynau
Opsiynau:
Ydy
Disgrifiad o’r opsiynau:
1) Option to extend the term of Framework Agreement
The term of the Framework Agreement is for an initial term of eight years with the right to extend the term of the Framework Agreement for up to a further two years to make a maximum possible term of ten years. HS2 Ltd has the right to extend the term of the Framework Agreement from eight to ten years in the event that the advertised Scope cannot be completed during the initial eight year term due to changes to the programme, including but not limited to land access delays or prolongation of the programme due to consenting issues.
II.2.13) Gwybodaeth am Gronfeydd yr Undeb Ewropeaidd
Mae'r broses gaffael yn gysylltiedig â phrosiect a/neu raglen a ariennir gan gronfeydd yr Undeb Ewropeaidd:
Na
II.2.14) Gwybodaeth ychwanegol
Refer to VI.3) Additional information in this Contract Notice below.
Rhif y Lot 2
II.2.1) Teitl
Lot 2 - Ground Investigation Contractor (GIC)
II.2.2) Cod(au) CPV ychwanegol
45111200
45111230
45120000
II.2.3) Man cyflawni
Cod NUTS:
UK
II.2.4) Disgrifiad o’r caffaeliad
HS2 Ltd has appointed 8 Contractors to Lot 2 which is for the acquisition of geotechnical, hydrogeological and geo-environmental data through surveys, the excavation and detailed logging of exploratory holes, and in-situ and laboratory testing, culminating in the production of factual reports across the Phase Two route, some land of which will be in areas of historic mining. The Framework Agreement has a duration of 8 years with works/services anticipated to be undertaken over a four-year period during that term although works/services may extend over a longer period and further HS2 Ltd retains the option to extend the Framework Agreement for a further two years in the event of delays to the GI programme (see II.2.11 (Information about options) for further information). Further works may be called off under the Framework Agreement as optional scope at other HS2 sites or by Contracting Bodies other than HS2 Ltd (see VI.3 below).
II.2.5) Meini prawf dyfarnu
Maes prawf ansawdd: Technical
/ Pwysoliad: 70
Maen prawf cost: Commercial
/ Pwysoliad: 30
II.2.11) Gwybodaeth am opsiynau
Opsiynau:
Ydy
Disgrifiad o’r opsiynau:
1) Option to extend the term of Framework Agreement
The term of the Framework Agreement is for an initial term of eight years with the right to extend the term of the Framework Agreement for up to a further two years to make a maximum possible term of ten years. HS2 Ltd has the right to extend the term of the Framework Agreement from eight to ten years in the event that the advertised Scope cannot be completed during the initial eight year term due to changes to the programme, including but not limited to land access delays or prolongation of the programme due to consenting issues.
II.2.13) Gwybodaeth am Gronfeydd yr Undeb Ewropeaidd
Mae'r broses gaffael yn gysylltiedig â phrosiect a/neu raglen a ariennir gan gronfeydd yr Undeb Ewropeaidd:
Na
II.2.14) Gwybodaeth ychwanegol
Refer to VI.3) Additional information in this Contract Notice below.
Section IV: Gweithdrefn
IV.1) Disgrifiad
IV.1.1) Y math o weithdrefn
negodi gyda galwad am gystadleuaeth
IV.1.3) Gwybodaeth am gytundeb fframwaith neu system brynu ddynamig
Mae'r broses gaffael yn golygu sefydlu cytundeb fframwaith gydag un gweithredwr.
IV.1.8) Gwybodaeth am Gytundeb Caffael y Llywodraeth (GPA)
The procurement is covered by the Government Procurement Agreement:
Ydy
IV.2) Gwybodaeth weinyddol
IV.2.1) Cyhoeddiad blaenorol mewn perthynas â’r weithdrefn hon
Rhif yr hysbysiad yn OJ S:
2021/S 000-015986
Section V: Dyfarnu contract
Rhif y Lot: 1
Rhif Contract: C1000_3089
Teitl: Lot 1- Ground Investigation Partner (GIP)
Dyfernir contract/lot:
Ydy
V.2 Dyfarnu contract
V.2.1) Y dyddiad y daeth y contract i ben
07/09/2023
V.2.2) Gwybodaeth am dendrau
Nifer y tendrau a ddaeth i law: 1
Dyfarnwyd y contract i gr?p o weithredwyr economaidd:
Na
V.2.3) Enw a chyfeiriad y contractwr
AECOM Limited
London
UK
NUTS: UK
BBaCh yw’r contractwr:
Na
V.2.4) Gwybodaeth am werth y contract/lot (heb gynnwys VAT)
Amcangyfrif cychwynnol o gyfanswm gwerth y contract/lot: 85 000 000.00 GBP
Cyfanswm gwerth y contract/lot: 85 000 000.00 GBP
V.2.5) Gwybodaeth am is-gontractio
Section V: Dyfarnu contract
Rhif y Lot: 2
Rhif Contract: C1000_3089
Teitl: Lot 2- Ground Investigation Contractor (GIC)
Dyfernir contract/lot:
Ydy
V.2 Dyfarnu contract
V.2.1) Y dyddiad y daeth y contract i ben
07/09/2023
V.2.2) Gwybodaeth am dendrau
Nifer y tendrau a ddaeth i law: 9
Dyfarnwyd y contract i gr?p o weithredwyr economaidd:
Ydy
V.2.3) Enw a chyfeiriad y contractwr
BAM Nuttall Ltd (TA BAM Ritchies)
Glasgow
UK
NUTS: UK
BBaCh yw’r contractwr:
Na
V.2.3) Enw a chyfeiriad y contractwr
Fugro GeoServices Ltd
Wallingford
UK
NUTS: UK
BBaCh yw’r contractwr:
Na
V.2.3) Enw a chyfeiriad y contractwr
Geotechnical Engineering Limited
Gloucester
UK
NUTS: UK
BBaCh yw’r contractwr:
Na
V.2.3) Enw a chyfeiriad y contractwr
RPS
Almondsbury, Bristol
UK
NUTS: UK
BBaCh yw’r contractwr:
Na
V.2.3) Enw a chyfeiriad y contractwr
SOCOTEC UK Ltd
Burton on Trent
UK
NUTS: UK
BBaCh yw’r contractwr:
Na
V.2.3) Enw a chyfeiriad y contractwr
Soil Engineering Geoservices Limited
Leeds
UK
NUTS: UK
BBaCh yw’r contractwr:
Na
V.2.3) Enw a chyfeiriad y contractwr
Strata Geotechnics (part of Van Elle Ltd)
Kirkby-in-Ashfield
UK
NUTS: UK
BBaCh yw’r contractwr:
Na
V.2.3) Enw a chyfeiriad y contractwr
Structural Soils Limited
Bedminster. Bristol
UK
NUTS: UK
BBaCh yw’r contractwr:
Na
V.2.4) Gwybodaeth am werth y contract/lot (heb gynnwys VAT)
Cyfanswm gwerth y contract/lot: 215 000 000.00 GBP
V.2.5) Gwybodaeth am is-gontractio
Mae’n debygol y caiff y contract ei is-gontractio
Section VI: Gwybodaeth ategol
VI.3) Gwybodaeth ychwanegol
Contracting Entity:
This Contract Notice is published by HS2 Ltd on behalf of itself and these Contracting Bodies:
• HS2 Ltd (including any successor to HS2 Ltd assuming HS2 Ltd's functions (in whole or in part) relevant to this Framework Agreement);
• The Infrastructure Manager;
• Route-wide Ground Investigation Contractors;
• Any other body as may assume delivery and/or ownership responsibilities in respect of the assets covered by this Framework Agreement;
• The future operator(s) the HS2 Phase 2 line.
VI.4) Gweithdrefnau adolygu
VI.4.1) Corff adolygu
High Court
Royal Courts Of Justice, Strand
London
WC2A 2LL
UK
VI.4.2) Corff sy’n gyfrifol am weithdrefnau cyfryngu
High Court
Royal Courts Of Justice, Strand
London
WC2A 2LL
UK
VI.5) Dyddiad anfon yr hysbysiad hwn
28/09/2023